Posted on October 10, 2019
PUBLIC NOTICE OF INTENT TO ISSUE AIR PERMITS
Florida Department of Environmental Protection
Division of Air Resource Management, Office of Permitting and Compliance
Draft Title V Air Operation Permit No. 1230001-087-AV
Draft Air Construction Permit Revision No. 1230001-086-AC
Foley Cellulose, LLC, Foley Mill
Taylor County, Florida
Applicant: The applicant for this project is Foley Cellulose, LLC. The applicant’s responsible official and mailing address are: Thomas Kicklighter, Vice President – General Manager, Foley Cellulose, LLC, Foley Mill, One Buckeye Drive, Perry, Florida 32348.
Facility Location: Foley Cellulose, LLC operates the existing Foley Mill, which is in Taylor County at One Buckeye Drive in Perry, Florida.
Project: The Foley Mill is an existing softwood Kraft Process Pulp Mill that manufactures bleached market pulps and dissolving cellulose pulps consisting of the following major activities: two Kraft pulp mills, chemical recovery, causticizing, purification (i.e. bleaching), papermaking, woodyard, and utility operations.
This project revised an underlying condition in Permit No. 1230001-077-AC to clarify the process used when the non-condensable gases are directed to the No. 1 Power Boiler and the No. 1 Bark Boiler. In addition, air construction Permit No. 1230001-086-AC incorporated the New Source Performance Standards Subpart Db of Title 40, Part 60, of the Code of Federal Regulations for the No. 1 Bark Boiler. This project did not cause an increase in tons/year of any pollutant; therefore, did not trigger PSD.
Permitting Authority: Applications for air construction permits are subject to review in accordance with the provisions of Chapter 403, Florida Statutes (F.S.) and Chapters 62-4, 62-210 and 62-212 of the Florida Administrative Code (F.A.C.). The proposed project is not exempt from air permitting requirements and an air permit is required to perform the proposed work.
Applications for Title V air operation permits are subject to review in accordance with the provisions of Chapter 403, Florida Statutes (F.S.) and Chapters 62-4, 62-210, and 62-213, of the Florida Administrative Code (F.A.C.). The proposed project is not exempt from air permitting requirements and a Title V air operation permit is required to operate the facility.
The Office of Permitting and Compliance in the Division of Air Resource Management is the Permitting Authority responsible for making a permit determination for these projects. The Permitting Authority’s physical address is: 2600 Blair Stone Road, Tallahassee, Florida. The Permitting Authority’s mailing address is: 2600 Blair Stone Road, MS #5505, Tallahassee, Florida 32399-2400. The Permitting Authority’s telephone number is 850/717-9000.
Project File: A complete project file is available for public inspection during the normal business hours of 8:00 a.m. to 5:00 p.m., Monday through Friday (except legal holidays), at the address indicated above for the Permitting Authority. The complete project file includes the draft air construction permit, the draft Title V air operation permit, the Statement of Basis, the application, and the information submitted by the applicant, exclusive of confidential records under Section 403.111, F.S. Interested persons may view the draft permits by visiting the following website: https://fldep.dep.state.fl.us/air/emission/apds/default.asp and entering the permit number shown above. Interested persons may contact the Permitting Authority’s project review engineer for additional information at the address or phone number listed above.
Notice of Intent to Issue Air Permit: The Permitting Authority gives notice of its intent to issue an air construction permit to the applicant for the project described above. The applicant has provided reasonable assurance that operation of proposed equipment will not adversely impact air quality and that the project will comply with all appropriate provisions of Chapters 62-4, 62-204, 62-210, 62-212, 62-296 and 62-297, F.A.C. The Permitting Authority will issue a final permit in accordance with the conditions of the proposed draft air construction permit unless a timely petition for an administrative hearing is filed under Sections 120.569 and 120.57, F.S. or unless public comment received in accordance with this notice results in a different decision or a significant change of terms or conditions.
The Permitting Authority gives notice of its intent to issue a Title V air operation permit to the applicant for the project described above. The applicant has provided reasonable assurance that continued operation of existing equipment will not adversely impact air quality and that the project will comply with all appropriate provisions of Chapters 62-4, 62-204, 62-210, 62-212, 62-213, 62-296 and 62-297, F.A.C. The Permitting Authority will issue a final Title V air operation permit in accordance with the conditions of the draft/proposed Title V air operation permit unless a timely petition for an administrative hearing is filed under Sections 120.569 and 120.57, F.S. or unless public comment received in accordance with this notice results in a different decision or a significant change of terms or conditions.
Comments: The Permitting Authority will accept written comments concerning the draft air construction permit for a period of 14 days from the date of publication of the Public Notice. Written comments must be received by the Permitting Authority by close of business (5:00 p.m.) on or before the end of this 14-day period. If written comments received result in a significant change to the draft air construction permit, the Permitting Authority shall revise the draft air construction permit and require, if applicable, another Public Notice. All comments filed will be made available for public inspection.
The Permitting Authority will accept written comments concerning the draft Title V air operation permit for a period of 30 days from the date of publication of the Public Notice. Because this permitting project is a revision to the existing Title V air operation permit, the revisions detailed in the Statement of Basis are the only portions of the permit that are open for public comment or challenge. Comments received related to the remainder of the permit will not be addressed during this permitting action. Written comments must be received by the close of business (5:00 p.m.), on or before the end of this 30-day period by the Permitting Authority at the above address. As part of his or her comments, any person may also request that the Permitting Authority hold a public meeting on this permitting action. If the Permitting Authority determines there is sufficient interest for a public meeting, it will publish notice of the time, date, and location in the Florida Administrative Register (FAR). If a public meeting is requested within the 30-day comment period and conducted by the Permitting Authority, any oral and written comments received during the public meeting will also be considered by the Permitting Authority. If timely received written comments or comments received at a public meeting result in a significant change to the draft Title V air operation permit, the Permitting Authority shall issue a revised draft Title V air operation permit and require, if applicable, another Public Notice. All comments filed will be made available for public inspection. For additional information, contact the Permitting Authority at the above address or phone number.
Petitions: A person whose substantial interests are affected by the proposed permitting decision may petition for an administrative hearing in accordance with Sections 120.569 and 120.57, F.S. Petitions filed by any persons other than those entitled to written notice under Section 120.60(3), F.S., must be filed within 14 days of publication of the Public Notice or receipt of a written notice, whichever occurs first. Under Section 120.60(3), F.S., however, any person who asked the Permitting Authority for notice of agency action may file a petition within 14 days of receipt of that notice, regardless of the date of publication. A petitioner shall mail a copy of the petition to the applicant at the address indicated above, at the time of filing. A petition for administrative hearing must contain the information set forth below and must be filed (received) with the Agency Clerk in the Office of General Counsel, 3900 Commonwealth Boulevard, MS 35, Tallahassee, Florida 32399-3000, Agency_Clerk@dep.state.fl.us, before the deadline. The failure of any person to file a petition within the appropriate time period shall constitute a waiver of that person’s right to request an administrative determination (hearing) under Sections 120.569 and 120.57, F.S., or to intervene in this proceeding and participate as a party to it. Any subsequent intervention (in a proceeding initiated by another party) will be only at the approval of the presiding officer upon the filing of a motion in compliance with Rule 28-106.205, F.A.C.
A petition that disputes the material facts on which the Permitting Authority’s action is based must contain the following information: (a) The name and address of each agency affected and each agency’s file or identification number, if known; (b) The name, address, any email address, telephone number and any facsimile number of the petitioner; the name, address, any email address, telephone number, and any facsimile number of the petitioner’s representative, if any, which shall be the address for service purposes during the course of the proceeding; and an explanation of how the petitioner’s substantial interests will be affected by the agency determination; (c) A statement of when and how each petitioner received notice of the agency action or proposed decision; (d) A statement of all disputed issues of material fact. If there are none, the petition must so indicate; (e) A concise statement of the ultimate facts alleged, including the specific facts the petitioner contends warrant reversal or modification of the agency’s proposed action; (f) A statement of the specific rules or statutes the petitioner contends require reversal or modification of the agency’s proposed action including an explanation of how the alleged facts relate to the specific rules or statutes; and, (g) A statement of the relief sought by the petitioner, stating precisely the action the petitioner wishes the agency to take with respect to the agency’s proposed action. A petition that does not dispute the material facts upon which the Permitting Authority’s action is based shall state that no such facts are in dispute and otherwise shall contain the same information as set forth above, as required by Rule 28-106.301, F.A.C.
Because the administrative hearing process is designed to formulate final agency action, the filing of a petition means that the Permitting Authority’s final action may be different from the position taken by it in this written notice of Intent to Issue Air Permit. Persons whose substantial interests will be affected by any such final decision of the Permitting Authority on the application have the right to petition to become a party to the proceeding, in accordance with the requirements set forth above.
Extension of Time: Under Rule 62-110.106(4), F.A.C., a person whose substantial interests are affected by the Department’s action may also request an extension of time to file a petition for an administrative hearing. The Department may, for good cause shown, grant the request for an extension of time. Requests for extension of time must be filed with the Office of General Counsel of the Department at 3900 Commonwealth Boulevard, Mail Station 35, Tallahassee, Florida 32399-3000, or via electronic correspondence at Agency_Clerk@dep.state.fl.us, before the deadline for filing a petition for an administrative hearing. A timely request for extension of time shall toll the running of the time period for filing a petition until the request is acted upon.
Mediation: Mediation is not available for this proceeding.
Objections: Finally, pursuant to 42 United States Code (U.S.C.) Section 7661d(b)(2), any person may petition the Administrator of the EPA within 60 days of the expiration of the Administrator’s 45-day review period as established at 42 U.S.C. Section 7661d(b)(1), to object to the issuance of any Title V air operation permit. Any petition shall be based only on objections to the permit that were raised with reasonable specificity during the 30-day public comment period provided in the Public Notice, unless the petitioner demonstrates to the Administrator of the EPA that it was impracticable to raise such objections within the comment period or unless the grounds for such objection arose after the comment period. Filing of a petition with the Administrator of the EPA does not stay the effective date of any permit properly issued pursuant to the provisions of Chapter 62-213, F.A.C. Petitions filed with the Administrator of EPA must meet the requirements of 42 U.S.C. Section 7661d(b)(2) and must be filed with the Administrator of the EPA at: U.S. Environmental Protection Agency, Office of the Administrator, 1200 Pennsylvania Avenue, N.W., Mail Code: 1101A, Washington, DC 20460. For more information regarding EPA review and objections, visit EPA’s Region 4 web site at: http://www2.epa.gov/caa-permitting/florida-proposed-title-v-permits.
NOTICE OF ENACTMENT OF ORDINANCE
BY THE CITY COUNCIL OF THE
CITY OF PERRY, FLORIDA
NOTICE IS HEREBY GIVEN that the ordinance, which title hereinafter appears, will be considered for enactment by the City Council of the City of Perry, Florida, at a public hearing on October 22, 2019, at 5:30 p.m., or as soon thereafter as the matter can be heard, in the City Council Meeting Room, City Hall, located at 224 South Jefferson Street, Perry, Florida. Copies of said ordinance may be inspected by any member of the public at the Office of the City Manager, City Hall, located at 224 South Jefferson Street, Perry, Florida, during regular business hours. On the date, time and place first above mentioned, all interested persons may appear and be heard concerning the ordinance. The amendment was previously noticed for a public hearing on August 27, 2019. The title of said ordinance reads, as follows:
ORDINANCE NO. 993
AN ORDINANCE OF THE CITY OF PERRY, FLORIDA, RELATING TO THE REZONING OF LESS THAN TEN CONTIGUOUS ACRES OF LAND, PURSUANT TO AN APPLICATION, Z 19-01, BY THE PROPERTY OWNER OF SAID ACREAGE, AMENDING THE OFFICIAL ZONING ATLAS OF THE CITY OF PERRY LAND DEVELOPMENT REGULATIONS; PROVIDING FOR REZONING FROM RESIDENTIAL, (CONVENTIONAL) SINGLE FAMILY-2 (RSF-2) TO RESIDENTIAL, (MIXED) SINGLE FAMILY/MOBILE HOME-2 (RSF/MH-2) OF CERTAIN LANDS WITHIN THE CORPORATE LIMITS OF THE CITY OF PERRY, FLORIDA; PROVIDING SEVERABILITY; REPEALING ALL ORDINANCES IN CONFLICT; AND PROVIDING AN EFFECTIVE DATE
The public hearing may be continued to one or more future dates. Any interested party shall be advised that the date, time and place of any continuation of the public hearing shall be announced during the public hearing and that no further notice concerning the matter will be published, unless said continuation exceeds six calendar weeks from the date of the above referenced public hearing.
All persons are advised that, if they decide to appeal any decision made at the public hearing, they will need a record of the proceedings and, for such purpose, they may need to ensure that a verbatim record of the proceedings is made, which record includes the testimony and evidence upon which the appeal is to be based.
Any person requiring auxiliary aids and services at this meeting may contact the City Manager’s Office at 850.584.7161 Ext. 113 at least 48 hours prior to the meeting. If you are hearing or speech impaired, please contact the Florida Relay Service at 800.955.8770 (voice) or 800.955.8771 (TTY).